The new Aberdeen Western Periphery Route or AWPR is set to reduce congestion problems, improve safety and lower pollution levels within the Granite City by creating a new bypass from Balmedie to Tipperty.

Drivers in and around Aberdeen won’t have failed to notice that construction of the new road is well underway. Naturally, this has led to some route disruption while the construction of new junctions and slip roads start to take shape. We want to make sure drivers and their passengers are enjoying car journeys as much as possible during the next few weeks, so we have provided information on traffic management for each section – keeping you driving forward and not round the bend! Transport Scotland has split traffic management into three sections as follows:

Northern Section (River Don to Tipperty)

U19C Leuchlands to Cranbog to Sheilhill Road

Week commencing 01/10/16: This road will be closed permanently from Tuesday 29 March 2016 to the opening of the new U19C to safely facilitate AWPR and utility works. A local diversion will be in place whilst the new U19C is under construction

B999 Aberdeen to Tarves Road

Week commencing 01/10/16: 2 way temporary traffic signals will be in place from Monday 03 October to Sunday 09 October, to safely facilitate AWPR enabling works.

A90 Main Carriageway (Between Murcar Roundabout and Easter Hatton)

Week commencing 01/10/16: Lane closures will be in place on the A90 from 2000hrs Saturday 01 October to 0600hrs Sunday 02 October, to safely facilitate AWPR works.

A90 Balmedie flyer

Week commencing 01/10/16: Lane closures will be in place on the A90, from 2000hrs Saturday 01 October to 0600hrs Sunday 02 October, to safely facilitate AWPR works. A 50mph speed restriction with lane width restrictions is in operation on the A90 northbound and southbound carriageways.

A90 (between Kier Farm and Old Road)

Week commencing 01/10/16: Lane closures will be in place on the A90, from 2000hrs Saturday 01 October to 0600hrs Sunday 02 October, to safely facilitate AWPR works.

A90 (Near Bridgend)

Week commencing 01/10/16: Lane closures will be in place on the A90, from 2000hrs Saturday 01 October to 0600hrs Sunday 02 October, to safely facilitate AWPR works.

Westfield Road

Week commencing 01/10/16: This road will be closed permanently from Monday 18 April 2016 to the opening of the new Westfield Road to safely facilitate AWPR and utility works. Local diversions will be in place whilst the road closure is in operation.

Mill Road, Foveran

Week commencing 01/10/16: This road will be closed permanently from Monday 11 July 2016 until the opening of the new Mill Road to safely facilitate AWPR and utility works. Local diversions will be in place while the new Mill Road is under construction.

Pitmillan Road

Week commencing 01/10/16: 2 way temporary traffic signals will be in operation, between 2000hrs and 0600hrs, from Saturday 24 September to Sunday 25 October, to safely facilitate AWPR works.

Central Section (River Dee to River Don)

Milltimber Brae

Week commencing 01/10/16: A road closure will be in place on the U133C Milltimber Brae from 0600hrs Friday 08 April 2016 for a period of approximately 12 months, to safely facilitate utility works. Local diversions will be in place whilst the road closure is in operation.

A944 Main Carriageway

Week commencing 01/10/16: A lane closure will be in place on the A944 eastbound carriageway, between Westhill and Kingswells, between 0600hrs and 2000hrs, from Saturday 01 October to Sunday 02 October, to safely facilitate AWPR enabling works.

C93C Clinterty to Kingsford Road

Week commencing 01/10/16: A road closure will be in place on the C93C Clinterty to Kingsford Road, from 2000hrs Friday 30 September to 0600hrs Monday 03 October to safely facilitate AWPR works. Local diversions will be in place whilst the road closure is in operation.

C89C Chapel of Stoneywood to Fairley Road

Week commencing 01/10/16: 2 way temporary traffic signals will be in operation between 0930hrs and 1530hrs, from Monday 03 October to Friday 07 October, to safely facilitate AWPR enabling works. A road closure will be in place on the C89C from 2000hrs Friday 07 September to 0600hrs Monday 10 October to safely facilitate AWPR enabling works. Local diversions will be in place whilst the road closure is in operation.

A96 Main Carriageway

Week commencing 01/10/16: Lane closures will be in place on the A96 northbound and southbound carriageways, between 2000hrs and 0600hrs, from Wednesday 05 October to Thursday 13 October, to safely facilitate AWPR utility works.

Southern Section (Stonehaven/Charleston to River Dee)

A90 Main Carriageway

Week commencing 01/10/16: Lane closures will be in place on the A90 southbound carriageway, between 0930hrs and 1530hrs, from Saturday 01 October to Friday 07 October, to safely facilitate AWPR works.

B979 (South of junction with A90 northbound slip roads)

Week commencing 01/10/16: 2 way manually controlled traffic signals will be in operation between 0700hrs and 1900hrs, from Monday to Saturday each week until mid-October 2016, to safely facilitate AWPR enabling works.

B979 (West of junction with A90 northbound slip roads)

Week commencing 01/10/16: 2 way manually controlled traffic signals will be in operation between 0700hrs and 1900hrs, from Monday to Saturday each week until mid-October 2016, to safely facilitate AWPR enabling works.

A90 Charleston flyer

Week commencing 01/10/16: Lane closures will be in place on the A90 from 2000hrs Friday 30 September to 0600hrs Monday 03 October, to safely facilitate AWPR works. Lane closures will be in place on the A90, between 2000hrs and 0600hrs, from Monday 03 October to Friday 07 October, to safely facilitate AWPR works. These works are part of the overall Charleston Junction works.

Findon Junction to A90 Northbound Merge

Week commencing 01/10/16: Lane closures will be in place on the A90 from 2000hrs Friday 30 September to 0600hrs Monday 03 October, to safely facilitate AWPR works.

Lane closures will be in place on the A90, between 2000hrs and 0600hrs, from Monday 03 October to Friday 07 October, to safely facilitate AWPR works.

A90 to A956 Northbound Diverge

Week commencing 01/10/16: Lane closures will be in place on the A90 from 2000hrs Friday 30 September to 0600hrs Monday 03 October, to safely facilitate AWPR works.

Lane closures will be in place on the A90, between 2000hrs and 0600hrs, from Monday 03 October to Friday 07 October, to safely facilitate AWPR works.

A956 to A90 Northbound Merge

Week commencing 01/10/16: Lane closures will be in place on the A90 from 2000hrs Friday 30 September to 0600hrs Monday 03 October, to safely facilitate AWPR works.

Lane closures will be in place on the A90, between 2000hrs and 0600hrs, from Monday 03 October to Friday 07 October, to safely facilitate AWPR works.

A90 to A956 Southbound Diverge

Week commencing 01/10/16: Lane closures will be in place on the A90 from 2000hrs Friday 30 September to 0600hrs Monday 03 October, to safely facilitate AWPR works.

Lane closures will be in place on the A90, between 2000hrs and 0600hrs, from Monday 03 October to Friday 07 October, to safely facilitate AWPR works.

A956 Main Carriageway

Week commencing 01/10/16: Lane closures will be in place from 2000hrs Friday 30 September to 0600hrs Monday 03 October, to safely facilitate AWPR works.

Lane closures will be in place, between 2000hrs and 0600hrs, from Monday 03 October to Friday 07 October, to safely facilitate AWPR works.

Weekly traffic management updates are managed on the Transport Scotland website. Make sure you keep track of any changes right up until project completion due Spring 2018.